Tanners Drive

Tanners Drive

Industrial

Project: Internal and external refurbishment
Location: Milton Keynes
Contracts Value: £263,000
Duration: 14 weeks

External works included respraying the cladding, installing new windows and fitting new external gaskets. Internally the building was refurbished throughout which included installing new ceilings, laying new carpets and painting the warehouse floor. Replaced two roller shutter doors with new electrical doors. The works also included the installation of a new kitchen complete with electrics, new toilet facilities including vanity units and disabled facilities.
Upstairs the portioning walls was stripped out creating an open plan office with new lighting, electrical and data trunking, new ceilings and carpet finishes.