East Dulwich Community Hospital

Health

Project: External and internal refurbishment of hospital.
Location: East Dulwich Community Hospital, London
Contract Value: £500,000
Duration: 20 weeks

The external aspects of this project involved cleaning and repairing external brickwork, undertaking specialist stonework repairs to walkways and replacing windows.  Internally we installed point of use water heaters in many areas of the hospital.

The project had to be carefully planned to cause minimum disruption to staff and patients, and was further complicated by the considerable amounts of asbestos present.  In addition we had to work within the requirements of an L8 Risk Assessment in respect of Legionella bacteria control.